Ques:- Explain a critical path in schedule network diagram?
Asked In :-
Muvi Entertainment, AroDek, Mundrisoft Solutions LLP, Apttus Software, Black and White Business Solutions, Quale Infotech, Visionet Systems, Globant India, Skill Mine Technologies, Agilysys, Inc,
Right Answer:
The critical path in a schedule network diagram is the longest sequence of dependent tasks that determines the shortest time to complete a project. Any delay in the tasks on the critical path will directly impact the project's overall completion time.
The critical path in a schedule network diagram is the longest sequence of dependent tasks that determines the shortest time to complete a project. Any delay in the tasks on the critical path will directly impact the project's overall completion time.